Stingy credit markets and high regulatory hurdles have spurred Houston-based Dynegy to step back from new coal-fired power plant projects by ending a joint venture with LS Power Associates.
Dynegy will keep the right to expand its 27 existing coal, natural gas and oil-fired plants in 13 states, and it retains stakes in a pair of Texas and Arkansas coal projects.
But Dynegy will pay New York-based LS Power $19 million as part of the split and let it take full ownership of new projects under consideration in Arkansas, Georgia, Iowa, Michigan and Nevada.
Shares of Dynegy closed up 38 cents, or 19 percent, to $2.38 on Friday.
Dynegy Chairman and CEO Bruce Williamson said the power plant development landscape has changed since the company entered into the joint venture with LS in the fall of 2006. Funding new projects is much more difficult given the worldwide credit crunch and the possibility of new climate change legislation under the Obama administration.
"In light of these market circumstances, Dynegy has elected to focus development activities and investments around our own portfolio where we control the option to develop and can manage the costs being incurred more closely," Williamson said in a statement.
Dynegy's move appears to be good news for those who oppose new coal-fired power plants, such as one near Waterloo, Iowa. Here is the Waterloo-Cedar Falls Courier's take on the story:
The future of a proposed coal-fired power plant near Waterloo became a little cloudier Friday when Texas-based Dynegy Inc. announced that it and New Jersey-based LS Power Associates were dissolving their joint venture to develop that plant and others in several states.
The move transfers to LS Power full ownership and developmental rights associated with various "greenfield" projects in several states, including the 750-megawatt Elk Run Energy Station proposed for construction northeast of Waterloo.
[...]
Separation from Dynegy puts the Elk Run plans in doubt, said Don Shatzer, a member of Community Energy Solutions, which opposes the Elk Run Energy project.
"LS Power has no experience developing/operating coal plants and so is unlikely to proceed (without) a new partner," Shatzer said in an e-mail note.
Bruce Nilles, director of the Sierra Club's National Coal Campaign, shares Shatzer's opinion, according to The Houston Chronicle.
This sounds quite promising, although neither the Houston Chronicle nor the Waterloo-Cedar Falls Courier were able to get a comment from LS Power on whether it will continue to pursue this project.
Dynegy's move vindicates the actions of all those who worked hard to prevent the Waterloo plant from being built (more details on that are at Bleeding Heartland).